The week of May 15, construction will begin in earnest with heavy equipment on site to begin earthwork. Dump trucks will arrive, be filled and leave the site.
The week of May 8 activities will continue with the removal of the existing fence and the installation of the construction fence which will block the sidewalk during construction. Also, noise and dust monitors will be installed on site.
Activities are planned on the site beginning the week of May 1. During this week surveyors will be on-site and erosion controls will be installed around the property perimeter. Erosion controls involves the installation of an impermeable barrier buried a foot deep and extending two feet above ground. Additionally, there will be dump trucks arriving on site to lay down crushed rock that will establish a driveway for future truck traffic on site. The driveway will help control dirt from leaving the site and prevent trucks from waiting in the street.