TRAFFIC ALERT: As excavation of the rainwater detention tank continues, empty dump trucks will enter the site through an entrance on Ashby. The trucks will be loaded and exit onto Bissonnet ensuring traffic flow. Traffic control will be positioned at Ashby and Bissonnet for the safety of drivers entering Bissonnet from Ashby. This activity is scheduled throughout August.
Earthwork, moving dirt with onsite equipment while dump trucks haul dirt.
Install new utility lines.
Drill auger cast piles with onsite rig, concrete trucks haul on to the site.
Week of 08/14:
Earthwork, moving dirt with onsite equipment while dump trucks haul dirt.
Install new utility lines.
Drill auger cast piles with onsite rig, concrete trucks haul on to the site.
Week of 08/21:
Earthwork, moving dirt with onsite equipment while dump trucks haul dirt.
Install new utility lines.
Drill auger cast piles with onsite rig, concrete trucks haul on to the site.